Fuel distribution terminal in Hertfordshire
As principal contractor under CDM, Riverside Engineering Services Ltd managed the fabrication and installation of pipework and structural steelwork to convert an existing ground fuel storage site to also store and distribute aviation fuel. The project also included the introduction of extensive fire fighting systems. All pre-fabrication completed off site in Dundee. All installation carried out on site by RESL personnel. Project duration was 20 months, with a total value of approximately £4,500,000.
Process modules for north sea
The fabrication and fit out of large process modules for Norwegian sector of the North Sea.
Within scope of supply was fabrication of main structures, all pipework and tank fabrication, installation
of valves and equipment, load test and NDT, painting and final fit out. Completed units were loaded out
over the quayside in Dundee at our adjacent deep-water berths.
Total value approximately £440,000.